The BCRP Components
The BCRP process consists of:
Stage 1 (BCRP Steps 1, 2 & 3) - A desktop assessment of the project drawings, the Contract with the Owner, verification of Contract Sum and project costing and the determination of the number of inspections required in Step 4 of the BCRP process.
Stage 1 (BCRP Steps 1, 2 & 3) will be conducted when all requirements are received and will be concluded in the next business day.
Any document shortcomings will be highlighted, discussed with you and resolved.
The BCRP123 Confirmation will be issued to you with a copy to the Broker when BCRP Steps 1, 2 & 3 are satisfactorily concluded.
This will enable the Broker to review your Application for a Home Warranty for the project and issue the Home Warranty Certificate.
Stage 2 (BCRP Step 4)
<number> on-site inspections and <number> remote inspections will be conducted while the work in the project progresses. The outcomes of each inspections will be included in a BCRP 4 Report.
Stage 3 (BCRP Ste 5)
The Final BCRP Report will be issued when the project is completed, evidenced by the Occupation Certificate issued by the project's Certifier (PCA).
For projects that do not require a Certifier, the project's conclusion will be evidenced by a Completion Certificate issued by the Owner.
Quotation NMM quotes a sum of <sum> including GST for the BCRP Service for BCRP Steps 1-5 including travel and incidental costs.
A formal Quotation showing the breakdown is attached.
The Fee is fixed; if iCARE requests additional Inspections, NMM will absorb the additional costs.
If you are happy with the Quotation, please let us know.
When the Quotation is accepted, NMM will issue a Builder's Agreement identifying the terms and conditions of the BCRP Service and a list of documents required to undertake Stage 1 (BCRP Steps 1, 2 & 3).
Kind regards,
Mano
Hi <name> Thank you for confirming the acceptance of NMM's Quotation for BCRP Services for your project at <address>.
Please find attached:
The Builder's Agreement
Please sign and return it.
NMM Invoice
Please pay and provide evidence.
Details required
(1) The Architectural and Structural Drawings
(2) The Contract with the Owner
(3) Your quotation to the Owner
(4) Copy of the Project Application that was lodged with the Broker.
Regards,
mano
Hi <first name>,
Reference your Builder’s Agreement with NMM for BCRP Services for the proposed construction in <site address>.
NMM has conducted the BCRP Components 1, 2 & 3 review and is satisfied that the information provided complies with the criteria for BCRP assessment.
I have attached the BCRP123 CONFIRMATION.
Your Broker can proceed with processing the application for HBCF cover.
The BCRP Component 4 requires <number> inspections as follows:
Review No 01 - due approximately in <date>; ONSITE REMOTE when the floor is complete and frames / walls are in progress
Review No 02 - due approximately in <date>; ONSITE REMOTE when the superstructure is complete and finishes are in progress.
Please get in touch with us in time to schedule the reviews to proceed with BCRP Component 4 Review.
Wish you the best with the Project and look forward to working with you.
Regards,
mano.
Hi (name>,
The BCRP 4 & 5 Reports for the project at <address> are attached.
You may upload them to the Builder's Portal if you have access.
If you cannot access the Builder's Portal, please forward the Reports to your Broker for upload to iCARE's Portal.
Regards,
mano
Hi <name>,
Thank you for your email.
Your project at <site address> requires two remote BCRP inspections.
To collect info for the 1st remote inspection, please complete the form when you get a chance:
<link>.
Regards
Mano
Hi <name>,
Thank you for your email.
Happy to note the progress of your project at <site address>.
Please complete the form to gather info for the 2nd BCRP Inspection Report.
If an OC or an interim OC is available, please upload it to the form.
If not available, please forward it to me by email when issued.
Regards
Mano
Hi <first name> The BCRP Step 123 assessment for the project at <address> is complete and satisfactory.
Contract Sum
The Building Plans provided were assessed through software and costed on rates and prices in the 'Corelogic' database for NSW. A location adjustment of 1.8% and a Builder's Overheads and profits of 8% were applied. The Contract Sum of <contract sum> including GST for the project at <address> is determined as satisfactory.
Contract with the Owner
The Contract with the Owner is largely satisfactory.
BCRP123 Conformation
The BCRP123 Confirmation will be issued shortly.